Table 2.6.A. Biogenic Municipal Solid Waste: Consumption for Electricity Generation,
by Sector, 2016-January 2026 (Thousand Tons)

  Electric Power Sector  
Period Total (all sectors) Electric Utilities Independent
Power Producers
Commercial
Sector
Industrial
Sector
Annual Totals
2016 16,994 464 13,953 2,566 11
2017 16,348 422 13,381 2,537 8
2018 16,783 467 13,859 2,448 9
2019 15,559 297 12,941 2,310 10
2020 15,516 280 12,975 2,251 10
2021 15,223 252 12,442 2,521 7
2022 14,589 274 7,346 6,969 0
2023 13,916 283 6,960 6,674 0
2024 13,636 283 6,721 6,632 0
2025 13,279 267 6,620 6,392 0
Year 2024
January 1,182 21 582 578 0
February 1,065 17 531 516 0
March 1,105 13 565 527 0
April 1,070 20 504 546 0
May 1,172 29 567 575 0
June 1,137 27 555 555 0
July 1,201 28 595 578 0
August 1,228 27 604 597 0
Sept 1,117 24 560 533 0
October 1,118 27 544 547 0
November 1,113 24 554 535 0
December 1,129 25 558 546 0
Year 2025
January 1,106 17 558 531 0
February 989 15 499 474 0
March 1,075 16 525 534 0
April 1,070 23 521 525 0
May 1,115 24 574 517 0
June 1,118 22 563 533 0
July 1,186 23 603 560 0
August 1,165 25 581 558 0
Sept 1,119 25 545 549 0
October 1,097 25 539 533 0
November 1,113 25 554 533 0
December 1,127 26 557 544 0
Year 2026
January 1,036 20 520 496 0
Year to Date
2024 1,182 21 582 578 0
2025 1,106 17 558 531 0
2026 1,036 20 520 496 0
Rolling 12 Months Ending in January
2025 13,560 279 6,696 6,585 0
2026 13,209 269 6,583 6,357 0

Notes: Beginning with the collection of Form EIA-923 in January 2008, the methodology to allocate total fuel consumption for electricity generation and consumption for useful thermal output was changed.
The new methodology was retroactively applied to 2004-2007 data. See the Technical Notes (Appendix C) for further information. See Glossary for definitions.
Values for 2024 and prior years are final. Values for 2025 and 2026 are preliminary. See Technical Notes for a discussion of the sample design for the Form EIA-923 and predecessor forms.
Totals may not equal sum of components because of independent rounding.