Presented below are graphs and tables of the cost data for generators installed in 2023 based on data
collected by the 2023 Annual Electric Generator Report, Form EIA-860. The cost data for
certain generation technologies were omitted to avoid disclosure of individual company data.
EIA expects to publish construction cost data for generators installed in 2024 in September 2026.
Read EIA's Electric Power Data Guide.
Jump to group:
By selected sources and type:
Generators installed in 2023 by major energy source
All plants by major energy source |
Capacity-weighted average cost ($/kW) |
Solar |
1,617 |
Battery storage |
1,361 |
Wind |
1,738 |
Natural gas |
782 |
Petroleums liquids |
906 |
Total capacity (MW) |
At new plants |
At existing plants |
Solar |
18,883 |
265 |
Battery storage |
5,836 |
1,005 |
Wind |
5,404 |
588 |
Natural gas |
2,238 |
3,676 |
Petroleum liquids |
33 |
16 |
Number of plants |
At new plants |
At existing plants |
Solar |
478 |
9 |
Battery storage |
99 |
25 |
Wind |
33 |
2 |
Natural gas |
14 |
12 |
Petroleum liquids |
5 |
11 |
All plants by major energy source |
Total cost (billion $) |
Solar |
31.0 |
Battery storage |
9.3 |
Wind |
10.4 |
Natural gas |
4.6 |
Petroleum liquids |
0.0 |
Number of generators by major energy source |
At new plants |
At existing plants |
Solar |
487 |
17 |
Battery storage |
102 |
25 |
Wind |
35 |
3 |
Natural gas |
69 |
24 |
Petroleum liquids |
13 |
11 |
Average new plants capacity or additional capacity At existing plants |
At new plants |
At existing plants |
Solar |
40 |
29 |
Battery storage |
59 |
40 |
Wind |
164 |
294 |
Natural gas |
160 |
306 |
Petroleum liquids |
7 |
1 |
Generators installed in 2023 by prime mover
Capacity-weighted average cost per kilowatt of installed namepate capacity ($/kW) |
Capacity weighted-average cost ($/kW) |
Photovoltaic |
1,617 |
Energy storage, battery |
1,361 |
Onshore wind turbine |
1,738 |
Combustion turbine (as part of combined cycle) |
782 |
Combustion turbine |
562 |
Steam turbine (as part of combined cycle) |
1,122 |
Internal combustion engine |
1,248 |
Total included capacity(MW) |
At new plants |
At existing plants |
Photovoltaic |
18,883 |
265 |
Energy storage, battery |
5,836 |
1,005 |
Onshore wind turbine |
5,404 |
588 |
Combustion turbine (as part of combined cycle) |
861 |
1,436 |
Combustion turbine |
798 |
1,466 |
Steam turbine (as part of combined cycle) |
430 |
765 |
Internal combustion engine |
182 |
25 |
Number of generators |
At new plants |
At existing plants |
Photovoltaic |
487 |
17 |
Energy storage, battery |
102 |
25 |
Onshore wind turbine |
35 |
3 |
Combustion turbine (as part of combined cycle) |
2 |
5 |
Combustion turbine |
13 |
9 |
Steam turbine (as part of combined cycle) |
2 |
3 |
Internal combustion engine |
65 |
18 |
Average generator capacity at new or existing plants |
At new plants |
At existing plants |
Photovoltaic |
39 |
16 |
Energy storage, battery |
58 |
40 |
Onshore wind turbine |
154 |
196 |
Combustion turbine (as part of combined cycle) |
431 |
287 |
Combustion turbine |
61 |
163 |
Steam turbine (as part of combined cycle) |
215 |
255 |
Internal combustion engine |
3 |
1 |
Total construction cost |
total cost (billion $) |
Photovoltaic |
31.0 |
Energy storage, battery |
9.3 |
Onshore wind turbine |
10.4 |
Combustion turbine (as part of combined cycle) |
1.8 |
Combustion turbine |
1.3 |
Steam turbine (as part of combined cycle) |
1.3 |
Internal combustion engine |
0.2 |
Generators installed in 2023 by Census region
Census regions |
Capacity-weighted average cost ($/kW) |
South |
1,240 |
West |
1,550 |
Midwest |
1,632 |
Northeast |
2,366 |
Total included capacity |
At new plants |
At existing plants |
South |
13,678 |
4,301 |
West |
10,438 |
1,070 |
Midwest |
6,387 |
142 |
Northeast |
1,893 |
38 |
Number of plants |
At new plants |
At existing plants |
South |
196 |
13 |
West |
107 |
32 |
Midwest |
130 |
6 |
Northeast |
153 |
7 |
Number of generators |
At new plants |
At existing plants |
South |
253 |
27 |
West |
141 |
40 |
Midwest |
142 |
6 |
Northeast |
170 |
7 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
South |
70 |
331 |
West |
98 |
33 |
Midwest |
49 |
24 |
Northeast |
12 |
5 |
Census region |
Total cost (billion $) |
South |
22.3 |
West |
17.8 |
Midwest |
10.7 |
Northeast |
4.6 |
Generators installed in 2023 by top five states in capacity additions
State |
capacity-weighted average cost ($/kW) |
Texas |
1,211 |
California |
1,636 |
Florida |
1,055 |
Alabama |
981 |
Arizona |
1,377 |
Total included capacity |
At new plants |
At existing plants |
Texas |
6,601 |
919 |
California |
4,587 |
825 |
Florida |
1,810 |
1,203 |
Alabama |
913 |
1,468 |
Arizona |
1,791 |
148 |
Number of plants |
At new plants |
At existing plants |
Texas |
62 |
4 |
California |
56 |
10 |
Florida |
29 |
3 |
Alabama |
3 |
2 |
Arizona |
8 |
7 |
Number of generators |
At new plants |
At existing plants |
Texas |
104 |
9 |
California |
69 |
10 |
Florida |
30 |
5 |
Alabama |
4 |
5 |
Arizona |
14 |
7 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
Texas |
106 |
230 |
California |
82 |
82 |
Florida |
62 |
401 |
Alabama |
304 |
734 |
Arizona |
224 |
21 |
State |
total cost (billion $) |
Texas |
9.1 |
California |
8.9 |
Florida |
3.2 |
Alabama |
2.3 |
Arizona |
2.7 |
Natural gas generators installed in 2023 by technology
Natural gas plants by type |
Capacity-weighted average cost ($/kW) |
Combined cycle |
898 |
Combustion turbine |
562 |
Internal combustion engine |
1,354 |
Total included capacity (MW) |
At new plants |
At existing plants |
Combined cycle |
1,291 |
2,201 |
Combustion turbine |
798 |
1,466 |
Internal combustion engine |
150 |
9 |
Number of plants |
At new plants |
At existing plants |
Combined cycle |
2 |
3 |
Combustion turbine |
3 |
4 |
Internal combustion engine |
9 |
5 |
Number of generators |
At new plants |
At existing plants |
Combined cycle |
4 |
8 |
Combustion turbine |
13 |
9 |
Internal combustion engine |
52 |
7 |
Average new plants capacity or additional capacity At existing plants |
At new plants |
At existing plants |
Combined cycle |
645 |
734 |
Combustion turbine |
266 |
367 |
Internal combustion engine |
17 |
2 |
Total construction cost |
Total cost (billion $) |
Combined cycle |
3.1 |
Combustion turbine |
1.3 |
Internal combustion engine |
0.2 |
Natural gas generators installed in 2023 at combined-cycle plants by prime mover
Natural gas combined cycle plants by component |
Capacity-weighted average cost ($/kW) |
Combustion turbine
(as part of combined cycle) |
782 |
Steam turbine
(as part of combined cycle) |
1,122 |
Total capacity |
At new plants |
At existing plants |
Combustion turbine
(as part of combined cycle) |
861 |
1,436 |
Steam turbine
(as part of combined cycle) |
430 |
765 |
Number of generators |
At new plants |
At existing plants |
Combustion turbine
(as part of combined cycle) |
2 |
5 |
Steam turbine
(as part of combined cycle) |
2 |
3 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
Combustion turbine
(as part of combined cycle) |
431 |
287 |
Steam turbine
(as part of combined cycle) |
215 |
255 |
Natural gas generators at combined-cycle plants by prime mover |
Total cost (billion $) |
Combustion turbine
(as part of combined cycle) |
1.8 |
Steam turbine
(as part of combined cycle) |
1.3 |
Solar PV generators installed in 2023 by Census region
Census regions |
Capacity-weighted average cost ($/kW) |
South |
1,543 |
West |
1,544 |
Midwest |
1,606 |
Northeast |
2,584 |
Total included capacity |
At new plants |
At existing plants |
South |
8,707 |
0 |
West |
5,422 |
220 |
Midwest |
3,624 |
45 |
Northeast |
1,131 |
0 |
Number of plants |
At new plants |
At existing plants |
South |
148 |
0 |
West |
87 |
8 |
Midwest |
107 |
1 |
Northeast |
136 |
0 |
Number of generators |
At new plants |
At existing plants |
South |
150 |
0 |
West |
87 |
16 |
Midwest |
107 |
1 |
Northeast |
143 |
0 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
South |
59 |
0 |
West |
62 |
28 |
Midwest |
34 |
45 |
Northeast |
8 |
0 |
Region |
Total cost (billion $) |
South |
13.4 |
West |
8.7 |
Midwest |
5.9 |
Northeast |
2.9 |
Solar PV generators installed in 2023 by top five states in capacity additions
Census regions |
capacity-weighted average cost ($/kW) |
Texas |
1,330 |
California |
1,639 |
Florida |
1,370 |
Ohio |
1,476 |
Arizona |
1,349 |
Total included capacity |
At new plants |
At existing plants |
Texas |
3,626 |
0 |
California |
2,170 |
133 |
Florida |
1,808 |
0 |
Ohio |
1,323 |
0 |
Arizona |
910 |
0 |
Number of plants |
At new plants |
At existing plants |
Texas |
20 |
0 |
California |
45 |
1 |
Florida |
29 |
0 |
Ohio |
11 |
0 |
Arizona |
6 |
0 |
Number of generators |
At new plants |
At existing plants |
Texas |
20 |
0 |
California |
45 |
1 |
Florida |
29 |
0 |
Ohio |
11 |
0 |
Arizona |
6 |
0 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
Texas |
181 |
0 |
California |
48 |
133 |
Florida |
62 |
0 |
Ohio |
120 |
0 |
Arizona |
152 |
0 |
State |
total cost (billion $) |
Texas |
4.8 |
California |
3.8 |
Florida |
2.5 |
Ohio |
2.0 |
Arizona |
1.2 |
Solar PV generators installed in 2023 by PV panel type and tracking system
Solar PV plants by tracking system |
Capacity-weighted average cost ($/kW) |
Crystalline silicon,
axis-based tracking |
1,563 |
Crystalline silicon,
fixed tilt |
2,635 |
Thin-film CdTe,
all types |
1,663 |
Other |
1,448 |
Total included capacity |
At new plants |
At existing plants |
Crystalline silicon,
axis-based tracking |
12,024 |
265 |
Crystalline silicon,
fixed tilt |
817 |
1 |
Thin-film CdTe,
all types |
3,962 |
0 |
Other |
2,081 |
0 |
Number of plants |
At new plants |
At existing plants |
Crystalline silicon,
axis-based tracking |
258 |
8 |
Crystalline silicon,
fixed tilt |
133 |
1 |
Thin-film CdTe,
all types |
60 |
0 |
Other |
27 |
0 |
Number of generators |
At new plants |
At existing plants |
Crystalline silicon,
axis-based tracking |
259 |
8 |
Crystalline silicon,
fixed tilt |
141 |
9 |
Thin-film CdTe,
all types |
60 |
0 |
Other |
27 |
0 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
Crystalline silicon,
axis-based tracking |
47 |
33 |
Crystalline silicon,
fixed tilt |
6 |
1 |
Thin-film CdTe,
all types |
66 |
0 |
Other |
77 |
0 |
Solar PV plants by tracking system |
Total cost (billion $) |
Crystalline silicon,
axis-based tracking |
19.2 |
Crystalline silicon,
fixed tilt |
2.2 |
Thin-film CdTe,
all types |
6.6 |
Other |
3.0 |
Solar PV generators installed in 2023 by total added capacity at plant
Plant size |
Capacity-weighted average cost ($/kW) |
1–5 MW |
2,909 |
5–10 MW |
2,348 |
10–100 MW |
1,772 |
Greater than 100 MW |
1,420 |
Total included capacity |
At new plants |
At existing plants |
1–5 MW |
735 |
6 |
5–10 MW |
127 |
19 |
10–100 MW |
7,065 |
108 |
Greater than 100 MW |
10,957 |
133 |
Number of plants |
At new plants |
At existing plants |
1–5 MW |
267 |
2 |
5–10 MW |
17 |
3 |
10–100 MW |
141 |
3 |
Greater than 100 MW |
53 |
1 |
Number of generators |
At new plants |
At existing plants |
1–5 MW |
271 |
10 |
5–10 MW |
18 |
3 |
10–100 MW |
145 |
3 |
Greater than 100 MW |
53 |
1 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
1–5 MW |
3 |
3 |
5–10 MW |
7 |
6 |
10–100 MW |
50 |
36 |
Greater than 100 MW |
207 |
133 |
Plant size |
total cost (billion $) |
1–5 MW |
2.2 |
5–10 MW |
0.3 |
10–100 MW |
12.7 |
Greater than 100 MW |
15.8 |
Wind generators installed in 2023 by Census region
Census region |
capacity-weighted average cost ($/kW) |
Midwest |
1,758 |
South |
1,468 |
Northeast and West |
2,114 |
Total included capacity |
At new plants |
At existing plants |
Midwest |
2,406 |
88 |
South |
1,613 |
500 |
Northeast and West |
1,386 |
0 |
Number of plants |
At new plants |
At existing plants |
Midwest |
15 |
1 |
South |
7 |
1 |
Northeast and West |
11 |
0 |
Number of generators |
At new plants |
At existing plants |
Midwest |
17 |
1 |
South |
7 |
2 |
Northeast and West |
11 |
0 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
Midwest |
160 |
88 |
South |
230 |
500 |
Northeast and West |
126 |
0 |
Census region |
Total cost (billion $) |
Midwest |
4.4 |
South |
3.1 |
Northeast and West |
2.9 |
Wind generators installed in 2023 by plant size
Plant size |
Capacity-weighted average cost ($/kW) |
1–100 MW |
2,260 |
100–200 MW |
1,846 |
Greater than 200 MW |
1,584 |
Total included capacity |
At new plants |
At existing plants |
1–100 MW |
479 |
88 |
100–200 MW |
2,059 |
0 |
Greater than 200 MW |
2,867 |
500 |
Number of plants |
At new plants |
At existing plants |
1–100 MW |
6 |
1 |
100–200 MW |
15 |
0 |
Greater than 200 MW |
12 |
1 |
Number of generators |
At new plants |
At existing plants |
1–100 MW |
8 |
1 |
100–200 MW |
15 |
0 |
Greater than 200 MW |
12 |
2 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
1–100 MW |
80 |
88 |
100–200 MW |
137 |
0 |
Greater than 200 MW |
239 |
500 |
Plant size |
Total cost (billion $) |
1–100 MW |
1.3 |
100–200 MW |
3.8 |
Greater than 200 MW |
5.3 |
Wind generators installed in 2023 by wind class
Class |
capacity-weighted average cost ($/kW) |
Class 1 and 2 |
1,704 |
Class 3 |
1,823 |
Total included capacity |
At new plants |
At existing plants |
Class 1 and 2 |
3,708 |
588 |
Class 3 |
1,696 |
0 |
Number of plants |
At new plants |
At existing plants |
Class 1 and 2 |
20 |
2 |
Class 3 |
13 |
0 |
Number of generators |
At new plants |
At existing plants |
Class 1 and 2 |
20 |
3 |
Class 3 |
15 |
0 |
Average new plant or additional capacity At existing plants |
At new plants |
At existing plants |
Class 1 and 2 |
185 |
294 |
Class 3 |
130 |
0 |
Plant size |
total cost (billion $) |
Class 1 and 2 |
7.3 |
Class 3 |
3.1 |
Notes:
- Data includes facilities with a total generator nameplate capacity of 1 megawatt (MW) or more. Solar data does not include distributed generation capacity.
- Government grants, tax benefits, or other incentives are excluded from these costs.
- Solar photovoltaic (PV) data are based on reported alternating current (AC) capacity and may differ from other cost and capacity estimates that use direct current (DC) ratings of PV panels.
- Petroleum liquids includes distillate fuel oil, jet fuel, kerosene, residual fuel oil, and waste oil.
- Biomass includes both liquid and gaseous biomass fuels.
- Some generation technologies were excluded from this analysis to avoid disclosure of individual company data.
- Average construction cost is based on the nameplate capacity weighted average cost per kilowatt of installed nameplate capacity.
- Total capacity is the sum of the nameplate capacity of generators included in each group.
- Average new capacity is based on the nameplate capacity of new plants or new additions of nameplate capacity to existing plants. New plants did not previously have operable units and are typically recently constructed. Existing plants have at least one previously operable generator and are not newly constructed.
- Totals may not equal sum of components due to independent rounding.
Data source: U.S. Energy Information Administration, Form EIA-860, Annual Electric Generator Report