Construction cost data for electric generators installed in 2016
Release date: August 6, 2018 | Next release date: July 2019
Presented below are graphs and tables of the cost data for generators installed in 2016 based on data collected by the 2016 Annual Electric Generator Report, Form EIA-860. The cost data for certain generation technologies were omitted to avoid disclosure of individual company data.
EIA expects to publish construction cost data for generators installed in 2017 in July 2019.
Read EIA's Electric Power Data Guide.
2016 Tables
Jump to group:
All generators by: major energy source | prime mover | Census region | top five states in capacity additions
By selected sources and type:
Natural gas
: technology | combined-cycle by prime mover
Solar PV:
Census region | top five states in Solar PV capacity additions | PV panel type and tracking system | total added capacity at plant
Wind:
Census region | total added capacity at plant | wind class
Generators installed in 2016 by major energy source
| All plants by major energy source |
capacity-weighted average cost ($/kW) |
| wind |
1,630 |
| solar |
2,434 |
| natural gas |
895 |
| hydro |
5,312 |
| battery storage |
1,763 |
| biomass |
2,198 |
| petroleum liquids |
1,672 |
| Total capacity (MW) |
at new plants |
at existing plants |
| wind |
8,561 |
193 |
| solar |
7,501 |
526 |
| natural gas |
3,221 |
4,722 |
| hydro |
256 |
124 |
| battery storage |
78 |
119 |
| biomass |
81 |
10 |
| petroleum liquids |
8 |
18 |
| Number of plants |
at new plants |
at existing plants |
| wind |
68 |
4 |
| solar |
427 |
13 |
| natural gas |
14 |
26 |
| hydro |
7 |
2 |
| battery storage |
10 |
9 |
| biomass |
10 |
5 |
| petroleum liquids |
2 |
10 |
| All plants by major energy source |
total cost (billion $) |
| wind |
14.3 |
| solar |
19.5 |
| natural gas |
7.1 |
| hydro |
2.0 |
| battery storage |
.3 |
| biomass |
.2 |
| petroleum liquids |
.04 |
| Number of generators by major energy source |
at new plants |
at existing plants |
| wind |
78 |
4 |
| solar |
472 |
25 |
| natural gas |
44 |
51 |
| hydro |
24 |
2 |
| battery storage |
11 |
9 |
| biomass |
33 |
16 |
| petroleum liquids |
11 |
15 |
| Average new plants capacity or additional capacity at existing plants |
at new plants |
at existing plants |
| wind |
126 |
48 |
| solar |
18 |
40 |
| natural gas |
230 |
182 |
| hydro |
37 |
62 |
| battery storage |
8 |
13 |
| biomass |
8 |
2 |
| petroleum liquids |
4 |
2 |
↓ notes
↑ top
Generators installed in 2016 by prime mover
↓ notes
↑ top
| Capacity-weighted average cost per kilowatt of installed namepate capacity ($/kW) |
capacity weighted-average cost ($/kW) |
| combustion turbine |
717 |
| combustion turbine (as part of combined cycle) |
1,011 |
| steam turbine (as part of combined cycle) |
1,021 |
| internal combustion engine |
1,379 |
| hydroelectric turbine |
5,312 |
| onshore wind turbine |
1,630 |
| photovoltaic |
2,434 |
| energy storage, battery |
1,763 |
| Total included capacity(MW) |
at new plants |
at existing plants |
| combustion turbine |
820 |
2,676 |
| combustion turbine (as part of combined cycle) |
1,250 |
1,176 |
| steam turbine (as part of combined cycle) |
797 |
748 |
| internal combustion engine |
443 |
151 |
| hydroelectric turbine |
256 |
124 |
| onshore wind turbine |
8,561 |
193 |
| photovoltaic |
7,501 |
526 |
| energy storage, battery |
78 |
119 |
| number of generators |
at new plants |
at existing plants |
| combustion turbine |
10 |
22 |
| combustion turbine (as part of combined cycle) |
5 |
5 |
| steam turbine (as part of combined cycle) |
3 |
6 |
| internal combustion engine |
70 |
49 |
| hydroelectric turbine |
24 |
2 |
| onshore wind turbine |
78 |
4 |
| photovoltaic |
472 |
25 |
| energy storage, battery |
11 |
9 |
| Average generator capacity at new or existing plants |
at new plants |
at existing plants |
| combustion turbine |
82 |
122 |
| combustion turbine (as part of combined cycle) |
250 |
235 |
| steam turbine (as part of combined cycle) |
266 |
125 |
| internal combustion engine |
6 |
3 |
| hydroelectric turbine |
11 |
62 |
| onshore wind turbine |
110 |
48 |
| photovoltaic |
16 |
21 |
| energy storage, battery |
7 |
13 |
| Total construction cost |
total cost (billion $) |
| combustion turbine |
2.5 |
| combustion turbine (as part of combined cycle) |
2.5 |
| steam turbine (as part of combined cycle) |
1.6 |
| internal combustion engine |
.8 |
| hydroelectric turbine |
2.0 |
| onshore wind turbine |
14.3 |
| photovoltaic |
19.5 |
| energy storage, battery |
.3 |
Generators installed in 2016 by Census region
↓ notes
↑ top
| Census regions |
capacity-weighted average cost ($/kW) |
| South |
1,420 |
| West |
2,314 |
| Midwest |
1,422 |
| Northeast |
2,677 |
| Total included capacity |
at new plants |
at existing plants |
| South |
8,931 |
3,817 |
| West |
5,767 |
1,415 |
| Midwest |
4,273 |
410 |
| Northeast |
734 |
69 |
| Number of plants |
at new plants |
at existing plants |
| South |
198 |
14 |
| West |
149 |
26 |
| Midwest |
89 |
18 |
| Northeast |
100 |
11 |
| Number of generators |
at new plants |
at existing plants |
| South |
242 |
42 |
| West |
186 |
46 |
| Midwest |
124 |
22 |
| Northeast |
121 |
12 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| South |
45 |
273 |
| West |
39 |
54 |
| Midwest |
48 |
23 |
| Northeast |
7 |
6 |
| Census region |
total cost (billion $) |
| South |
18.1 |
| West |
16.6 |
| Midwest |
6.7 |
| Northeast |
2.2 |
Generators installed in 2016 by top five states in capacity additions
↓ notes
↑ top
| State |
capacity-weighted average cost ($/kW) |
| California |
2,557 |
| Texas |
1,412 |
| Florida |
684 |
| Oklahoma |
1,598 |
| Virginia |
903 |
| Total included capacity |
at new plants |
at existing plants |
| California |
2,851 |
1,053 |
| Texas |
3,058 |
669 |
| Florida |
266 |
2,963 |
| Oklahoma |
1,634 |
65 |
tr>
| Virginia |
1,617 |
5 |
| Number of plants |
at new plants |
at existing plants |
| California |
84 |
13 |
| Texas |
18 |
3 |
| Florida |
11 |
4 |
| Oklahoma |
9 |
1 |
| Virginia |
8 |
2 |
| Number of generators |
at new plants |
at existing plants |
| California |
104 |
25 |
| Texas |
34 |
5 |
| Florida |
11 |
12 |
| Oklahoma |
11 |
1 |
| Virginia |
20 |
14 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| California |
34 |
81 |
| Texas |
170 |
223 |
| Florida |
24 |
741 |
| Oklahoma |
182 |
65 |
| Virginia |
202 |
2 |
| State |
total cost (billion $) |
| California |
10.0 |
| Texas |
5.3 |
| Florida |
2.2 |
| Oklahoma |
2.7 |
| Virginia |
1.5 |
Natural gas generators installed in 2016 by technology
↓ notes
↑ top
| Natural gas plants by type |
capacity-weighted average cost ($/kW) |
| combined cycle |
1,015 |
| combustion turbine |
717 |
| internal combustion engine |
1,207 |
| Total included capacity (MW) |
at new plants |
at existing plants |
| combined cycle |
2,046 |
1,923 |
| combustion turbine |
820 |
2,676 |
| internal combustion engine |
354 |
123 |
| Number of plants |
at new plants |
at existing plants |
| combined cycle |
3 |
6 |
| combustion turbine |
7 |
14 |
| internal combustion engine |
4 |
7 |
| Number of generators |
at new plants |
at existing plants |
| combined cycle |
8 |
11 |
| combustion turbine |
10 |
22 |
| internal combustion engine |
26 |
18 |
| Average new plants capacity or additional capacity at existing plants |
at new plants |
at existing plants |
| combined cycle |
682 |
321 |
| combustion turbine |
117 |
191 |
| internal combustion engine |
88 |
18 |
| Total construction cost |
total cost (billion $) |
| combined cycle |
4.0 |
| combustion turbine |
2.5 |
| internal combustion engine |
0.6 |
Natural gas generators installed in 2016 at combined-cycle plants by prime mover
| Natural gas combined cycle plants by component |
capacity-weighted average cost ($/kW) |
| combustion turbine |
1,011 |
| steam turbine |
1,021 |
| Total capacity |
at new plants |
at existing plants |
| combustion turbine |
1,250 |
1,176 |
| steam turbine |
797 |
748 |
| Number of generators |
at new plants |
at existing plants |
| combustion turbine |
5 |
5 |
| steam turbine |
3 |
6 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| combustion turbine |
250 |
235 |
| steam turbine |
266 |
125 |
| Natural gas generators at combined-cycle plants by prime mover |
total cost (billion $) |
| combustion turbine |
2.5 |
| steam turbine |
1.6 |
↓ notes
↑ top
| Solar PV plants by tracking system |
capacity-weighted average cost ($/kW) |
| solid biomass |
3,573 |
| gaseous biomass |
3,217 |
| Total included capacity |
at new plants |
at existing plants |
| solid biomass |
501 |
122 |
| gaseous biomass |
129 |
47 |
| Number of plants |
at new plants |
at existing plants |
| solid biomass |
13 |
2 |
| gaseous biomass |
34 |
14 |
| Number of generators |
at new plants |
at existing plants |
| solid biomass |
13 |
2 |
| gaseous biomass |
66 |
24 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| solid biomass |
39 |
61 |
| gaseous biomass |
4 |
3 |
| Solar PV plants by tracking system |
total cost (billion $) |
| solid biomass |
2.2 |
| gaseous biomass |
0.6 |
Solar PV generators installed in 2016 by Census region
↓ notes
↑ top
| Census regions |
capacity-weighted average cost ($/kW) |
| West |
2,575 |
| South |
2,150 |
| Midwest |
1,653 |
| Northeast |
3,190 |
| Total included capacity |
at new plants |
at existing plants |
| West |
4,577 |
508 |
| South |
2,339 |
10 |
| Midwest |
318 |
5 |
| Northeast |
267 |
3 |
| Number of plants |
at new plants |
at existing plants |
| West |
130 |
7 |
| South |
159 |
1 |
| Midwest |
55 |
3 |
| Northeast |
83 |
2 |
| Number of generators |
at new plants |
at existing plants |
| West |
152 |
19 |
| South |
159 |
1 |
| Midwest |
77 |
3 |
| Northeast |
84 |
2 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| West |
35 |
73 |
| South |
15 |
10 |
| Midwest |
6 |
2 |
| Northeast |
3 |
1 |
| Region |
total cost (billion $) |
| West |
13.1 |
| South |
5.0 |
| Midwest |
0.5 |
| Northeast |
.9 |
Solar PV generators installed in 2016 by top five states in Solar PV capacity additions
↓ notes
↑ top
| Census regions |
capacity-weighted average cost ($/kW) |
| California |
2,790 |
| North Carolina |
2,124 |
| Georgia |
2,051 |
| Utah |
1,895 |
| Nevada |
3,306 |
| Total included capacity |
at new plants |
at existing plants |
| California |
2,460 |
340 |
| North Carolina |
800 |
0 |
| Georgia |
732 |
0 |
| Utah |
689 |
0 |
| Nevada |
461 |
159 |
| Number of plants |
at new plants |
at existing plants |
| California |
76 |
5 |
| North Carolina |
107 |
0 |
| Georgia |
16 |
0 |
| Utah |
13 |
0 |
| Nevada |
6 |
1 |
| Number of generators |
at new plants |
at existing plants |
| California |
82 |
13 |
| North Carolina |
107 |
0 |
| Georgia |
16 |
0 |
| Utah |
13 |
0 |
| Nevada |
7 |
5 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| California |
32 |
68 |
| North Carolina |
7 |
|
| Georgia |
46 |
|
| Utah |
53 |
|
| Nevada |
77 |
159 |
| Region |
total cost (billion $) |
| California |
7.8 |
| North Carolina |
1.7 |
| Georgia |
1.5 |
| Utah |
1.3 |
| Nevada |
2.0 |
Solar PV generators installed in 2016 by PV panel type and tracking system
↓ notes
↑ top
| Solar PV plants by tracking system |
capacity-weighted average cost ($/kW) |
| crystalline silicon, fixed tilt |
2,351 |
| crystalline silicon, axis-based tracking |
2,243 |
| thin-film CdTe, fixed tilt |
3,630 |
| thin-film CdTe, axis-based tracking |
3,012 |
| other |
1,989 |
| Total included capacity |
at new plants |
at existing plants |
| crystalline silicon, fixed tilt |
1,293 |
21 |
| crystalline silicon, axis-based tracking |
4,826 |
12 |
| thin-film CdTe, fixed tilt |
385 |
190 |
| thin-film CdTe, axis-based tracking |
602 |
303 |
| other |
395 |
0 |
| Number of plants |
at new plants |
at existing plants |
| crystalline silicon, fixed tilt |
231 |
8 |
| crystalline silicon, axis-based tracking |
144 |
2 |
| thin-film CdTe, fixed tilt |
19 |
1 |
| thin-film CdTe, axis-based tracking |
17 |
2 |
| other |
16 |
0 |
| Number of generators |
at new plants |
at existing plants |
| crystalline silicon, fixed tilt |
250 |
9 |
| crystalline silicon, axis-based tracking |
152 |
2 |
| thin-film CdTe, fixed tilt |
34 |
5 |
| thin-film CdTe, axis-based tracking |
17 |
9 |
| other |
19 |
0 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| crystalline silicon, fixed tilt |
6 |
3 |
| crystalline silicon, axis-based tracking |
34 |
6 |
| thin-film CdTe, fixed tilt |
20 |
190 |
| thin-film CdTe, axis-based tracking |
35 |
151 |
| other |
25 |
0 |
| Solar PV plants by tracking system |
total cost (billion $) |
| crystalline silicon, fixed tilt |
3.1 |
| crystalline silicon, axis-based tracking |
10.9 |
| thin-film CdTe, fixed tilt |
2.1 |
| thin-film CdTe, axis-based tracking |
2.7 |
| other |
0.8 |
Solar PV generators installed in 2016 by total added capacity at plant
↓ notes
↑ top
| Plant size |
capacity-weighted average cost ($/kW) |
| 0.1-5 MW |
2,694 |
| 5-10 MW |
2,232 |
| 10-100 MW |
2,147 |
| 100-250 MW |
2,755 |
| Total included capacity |
at new plants |
at existing plants |
| 0.1-5 MW |
474 |
13 |
| 5-10 MW |
641 |
0 |
| 10-100 MW |
3,612 |
20 |
| 100-250 MW |
2,774 |
492 |
| Number of plants |
at new plants |
at existing plants |
| 0.1-5 MW |
193 |
8 |
| 5-10 MW |
114 |
0 |
| 10-100 MW |
99 |
2 |
| 100-250 MW |
21 |
3 |
| Number of generators |
at new plants |
at existing plants |
| 0.1-5 MW |
206 |
9 |
| 5-10 MW |
139 |
0 |
| 10-100 MW |
101 |
2 |
| 100-250 MW |
26 |
14 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| 0.1-5 MW |
2 |
2 |
| 5-10 MW |
6 |
0 |
| 10-100 MW |
36 |
10 |
| 100-250 MW |
132 |
164 |
| Plant size |
total cost (billion $) |
| 0.1-5 MW |
1.3 |
| 5-10 MW |
1.4 |
| 10-100 MW |
7.8 |
| 100-250 MW |
9.0 |
Wind generators installed in 2016 by Census region
↓ notes
↑ top
| Census region |
capacity-weighted average cost ($/kW) |
| South |
1,611 |
| Midwest and Northeast |
1,646 |
| West |
1,705 |
| Total included capacity |
at new plants |
at existing plants |
| South |
4,406 |
65 |
| Midwest and Northeast |
3,866 |
128 |
| West |
290 |
0 |
| Number of plants |
at new plants |
at existing plants |
| South |
22 |
1 |
| Midwest and Northeast |
39 |
3 |
| West |
7 |
0 |
| Number of generators |
at new plants |
at existing plants |
| South |
22 |
1 |
| Midwest and Northeast |
49 |
3 |
| West |
7 |
0 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| South |
200 |
65 |
| Midwest and Northeast |
99 |
43 |
| West |
41 |
0 |
| Census region |
total cost (billion $) |
| South |
7.2 |
| Midwest and Northeast |
6.6 |
| West |
.5 |
Wind generators installed in 2016 by total added capacity at plant
↓ notes
↑ top
| Plant size |
capacity-weighted average cost ($/kW) |
| 0.1-25 MW |
2,453 |
| 25-100 MW |
1,930 |
| 100-200 MW |
1,742 |
| 200-500 MW |
1,522 |
| Total included capacity |
at new plants |
at existing plants |
| 0.1-25 MW |
82 |
0 |
| 25-100 MW |
674 |
193 |
| 100-200 MW |
2,351 |
0 |
| 200-500 MW |
5,454 |
0 |
| Number of plants |
at new plants |
at existing plants |
| 0.1-25 MW |
17 |
0 |
| 25-100 MW |
12 |
4 |
| 100-200 MW |
16 |
0 |
| 200-500 MW |
23 |
0 |
| Number of generators |
at new plants |
at existing plants |
| 0.1-25 MW |
21 |
0 |
| 25-100 MW |
12 |
4 |
| 100-200 MW |
16 |
0 |
| 200-500 MW |
29 |
0 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| 0.1-25 MW |
5 |
0 |
| 25-100 MW |
56 |
48 |
| 100-200 MW |
147 |
0 |
| 200-500 MW |
237 |
0 |
| Plant size |
total cost (billion $) |
| 0.1-25 MW |
0.2 |
| 25-100 MW |
1.7 |
| 100-200 MW |
4.1 |
| 200-500 MW |
8.3 |
Wind generators installed in 2016 by wind class
↓ notes
↑ top
| Class |
capacity-weighted average cost ($/kW) |
| Class 1 and 2 |
1,661 |
| Class 3 |
1,569 |
| Total included capacity |
at new plants |
at existing plants |
| Class 1 and 2 |
5,762 |
65 |
| Class 3 |
2,799 |
128 |
| Number of plants |
at new plants |
at existing plants |
| Class 1 and 2 |
38 |
1 |
| Class 3 |
30 |
3 |
| Number of generators |
at new plants |
at existing plants |
| Class 1 and 2 |
38 |
1 |
| Class 3 |
40 |
3 |
| Average new plant or additional capacity at existing plants |
at new plants |
at existing plants |
| Class 1 and 2 |
152 |
65 |
| Class 3 |
93 |
43 |
| Plant size |
total cost (billion $) |
| Class 1 and 2 |
9.7 |
| Class 3 |
4.6 |
Notes:
- Data includes facilities with a total generator nameplate capacity of 1 megawatt (MW) or more. Solar data does not include distributed generation capacity.
- Government grants, tax benefits, or other incentives are excluded from these costs.
- Solar photovoltaic (PV) data are based on reported alternating current (AC) capacity and may differ from other cost and capacity estimates that use direct current (DC) ratings of PV panels.
- Petroleum liquids includes distillate fuel oil, jet fuel, kerosene, residual fuel oil, and waste oil.
- Some generating units that came online during 2016 were excluded from this analysis to avoid disclosure of individual company data.
- Average construction cost is based on the nameplate capacity weighted average cost per kilowatt of installed nameplate capacity.
- Total capacity is the sum of the nameplate capacity of generators included in each group.
- Average new capacity is based on the nameplate capacity of new plants or new additions of nameplate capacity to existing plants. New plants did not previously have operable units and are typically recently constructed. Existing plants have at least one previously operable generator and are not newly constructed.
- Totals may not equal sum of components due to independent rounding.
- Total Added Capacity at Plant categorization does not include the capacity existing prior to 2016.
- Wind class is defined as follows:
| Class |
Annual average wind speed |
Extreme 50-year gust |
Turbulence intensity |
| Class 1 - High Wind |
10 m/s (22.4 mph) |
70 m/s (156 mph) |
A: 0.210
B: 0.180 |
| Class 2 - Medium Wind |
8.5 m/s (19.0 mph) |
59.5 m/s (133 mph) |
A: 0.226
B: 0.191 |
| Class 3 - Low Wind |
7.5 m/s (16.8 mph) |
52.5 m/s (117 mph) |
A: 0.240
B: 0.200 |
| Class 4 - Very Low Wind |
6 m/s (13.4 mph) |
42 m/s (94 mph) |
A: 0.270
B: 0.220 |
Source: U.S. Energy Information Administration, Form EIA-860, Annual Electric Generator Report