Table 8. Selected LNG liquefaction projects existing and under construction
Project Country Capacity (millkion metric tons per year) Delivered cost to (dollars per million Btu) Scheduled start date
Sakhallin 2 Russia 9.6 8.70 2009
Pluto Australia 4.8 13.50 2012
Angola LNG Angola 5.2 9.90 2013
PNG LNG Papua New Guinea 6.9 10.50 2014
Queensland Curtis Australia 8.5 10.80 2014
Australia Pacific LNG Australia 9.0 11.20 2015
Gladstone LNG Australia 7.2 11.40 2015
Gordon Australia 15.6 12.30 2015
Sabine United States 18.0 9.90a
14.40b
2015
Ichthys Australia 8.4 10.20 2016
Wheatstone Australia 8.9 12.20 2016
Prelude Australia 3.6 10.40 2017

a$4 Henry Hub price.
b$8 Henry Hub price.
Source: EIA estimates based on capacities and capital costs from company websites and trade reports.
Note: 1 million metric tons of LNG is equivalent to approximately 48 billion cubic feet of natural gas.