| Crude oil and other petroleum liquids | Natural gas | Coal | Nuclear | Hydro | Other renewables | Total | |
|---|---|---|---|---|---|---|---|
| Primary energy consumption (quads) 2021 | 0.6 | 1.1 | <0.1 | -- | -- | <0.1 | 1.6 |
| Primary energy consumption (percentage) | 35.0% | 64.8% | <0.2% | -- | -- | <0.1% | 100.0% |
| Primary energy production (quads) 2021 | 5.8 | 0.8 | -- | -- | -- | <0.1 | 6.5 |
| Primary energy production (percentage) | 88.0% | 12.0% | -- | -- | -- | <0.1% | 100.0% |
| Electricity generation (terawatthours)a 2021 | 27.4 | 43.8 | -- | -- | -- | <0.1 | 71.2 |
| Electricity generation (percentage) | 38.5% | 61.5% | -- | -- | -- | <0.1% | 100.0% |
|
Data source: U.S. Energy Information Administration, Fitch Solutions Note: Quads=quadrillion British thermal units Note: Numbers may not add up because of independent rounding. aCrude oil and other petroleum liquids, natural gas, and coal generation proportions from Fitch Solutions, Kuwait Power Report, Q3 2023, were used to breakout aggregate fossil fuel generation from EIA’s International Energy Statistics. |
|||||||
| Project name | Additional oil production capacity (thousand b/d) | Additional natural gas production capacity (Bcf) | Announced start date | Notes |
|---|---|---|---|---|
| Jurassic natural gas field Phase 2 | 120 | 114 | 2018 | Installation of three early production facilities (EPFs) |
| Jurassic EPF-50 expansion | N/A | 13 | 2018 | Expansion of the original facility supporting the 2010 Jurassic Gas Project |
| Lower Fars heavy oil project Phase 1 | 60 | N/A | 2020 | South Ratqa field in northern Kuwait |
| GC-31 gathering facility | 100 | 23 | 2021 | Gathering center located in northern Kuwait |
| Khafji oil field in the Neutral Zone | N/A | 9 | 2021 | Natural gas pipeline from the offshore field installed |
| Khafji oil field in the Neutral Zone Phase 2 | N/A | 6 | 2023 | Second phase of the pipeline completed |
| Wafra oil field in the Neutral Zone | N/A | 15 | 2022 | Natural gas first captured from Wafra to be used for field operations and Kuwait’s power grid |
| Jurassic natural gas field—EPF 3 expansion | 10 | 38 | 2024 | |
| Jurassic natural gas field Phase 3—EPF 4 and 5 | 100 | 110 | 2024 | |
| Burgan GC-32 gathering facility | 120 | 30 | TBA | Project to increase Burgan oil field capacity; operated by Petrofac; under construction |
| Umm Niqa heavy oil field expansion | 30 | N/A | 2030 | |
| Lower Fars heavy oil project Phase 2 | 210 | N/A | 2040 | South Ratqa field in northern Kuwait; project not yet sanctioned |
| Durra natural gas field | 42 | 183 | TBA | Kuwait and Saudi Arabia agreed to co-develop the field in 2022. Oil and natural gas production are Kuwait’s shares only |
| Total | 792 | 541 | ||
Data source: Middle East Economic Survey, Fitch Solutions, Rystad Energy, Reuters, Kuwait Oil Company. |
||||
| Refinery | Owners | Capacity (thousand barrels per day [b/d]) | Notes |
|---|---|---|---|
| Crude oil and condensate refineries | |||
| Mina Abdullah | Kuwait National Petroleum Corporation | 454 | Clean Fuels Project upgrade for refinery completed September 2021 |
| Mina Al-Ahmadi | Kuwait National Petroleum Corporation | 346 | Clean Fuels Project upgrade for refinery completed August 2020 |
| Al Zour Unit 1 | Kuwait Integrated Petroleum Industries Company | 205 | Became operational in November 2022 with 205,000 b/d of capacity |
| Al Zour Unit 2 | Kuwait Integrated Petroleum Industries Company | 205 | Became operational in March 2023 with 205,000 b/d of capacity |
| Al Zour Unit 3 | Kuwait Integrated Petroleum Industries Company | 205 | Expected online in the second half of 2023 |
| Total | 1,415 | ||
Data source: Oil and Gas Journal, FACTS Global Energy, and Middle East Economic Survey |
|||
| Project name | Owners | Nameplate capacity (billion cubic feet per year) | Operational start year |
|---|---|---|---|
| Existing LNG import terminals | |||
| Al-Zour LNG Phase 1 | Kuwait Petroleum Corporation | 528 | July 2021 |
| Al-Zour LNG Phase 2 | Kuwait Petroleum Corporation | 528 | February 2022 |
| Total | 1,056 | ||
Data source: International Gas Union, 2022 World LNG Report, Middle East Economic Survey, Rigzone, Arab Times |
|||
| Project name | Fuel | Capacity (megawatts) | Notes |
|---|---|---|---|
| Az-Zour North Phases 2 and 3 | Natural gas | 2,700 | CCGT plant |
| Al-Khiran Phase 1 | Natural gas and oil | 1,800 | Gas turbine |
| Al Sabiya Phases 2 and 4 | Natural gas | 1,150 | CCGT plant |
| Nowaiseeb Phase 1 | Natural gas | 3,600 | CCGT plant |
| Al-Shygaya Renewable Energy Phases 2 and 3 | Solar | 3,500 | |
| Kabd project | Waste to energy | 80 | |
| Total | 12,830 | ||
Data source: Kuwait’s Ministry of Electricity & Water & Renewable Energy, Saudi Gulf Projects, Middle East Economic Survey, Times Kuwait, Power Technology |
|||